36. CPU Scheduling、SJF、Round Robin、Waiting Time
#OS-04-036中CPU SchedulingSJFRound RobinWaiting Time
Consider the following CPU scheduling result in a single-processor system (Gantt chart): runs from 0 to 2 ms, from 2 to 3 ms, from 3 to 8 ms, from 8 to 12 ms, from 12 to 18 ms. If all the five processes complete within 18 ms, which statement(s) are correct?